
Overburden Removal, Mining & Screening Phosphate in Orebodies (31+35)
-
Location of Project : Al Abiad Mine
-
Client : Jordanian Phosphate Company (JPMC)
-
Awarded date of Project : 10-2012
-
Quantities of Project :
-
Overburden removal (OB) quantities = 27.5 Million BCM
-
Mining Phosphate quantities =2.3 Million BCM
-
Screening & Crushing quantities = 2.78 Million Ton
-
Completion = 100 %
Scope of Work :
-
Overburden Removal using excavator & wheal loader and transport the OB to the waste yards and cleaning with dozing.
-
Phosphate Mining, Cleaning by graders and dozers
-
Transportation using dump truck to screen unit
-
Operate (closed vibrating plant system) which high productivity by max. the yield and min. rejection.
-
Feeding 50cm hopper by wheel loaders & dump trucks
-
Classification / separation of materials by Jaw & Rotary crusher
-
Crushing & sizing the materials to pass 100% of -8mm
-
All materials handled by conveyor belts then transport product to piles
-
Mixing & blending the product to get the required homogenous
-
Drying the product by solar sun and wind energy to reduce moisture content.
-
Hauling the oversize (reject) material to waste yards (Stockpiles) and dozing
-
All productivity maintenance activities of conveyor belts and vibrating screens plants performed by in house team.

Let's Work Together
Earthworks and Mining ...