Overburden Removal, Mining, Screening, Drying & Transporting Phosphate at Orebody 45
-
Location of Project : Al Abiad Mine - Jordan
-
Client : Jordanian Phosphate Mining Company (JPMC)
-
Awarded date of Project : 11-2022
-
Quantities of Project :
-
Overburden removal (OB) quantities = 20.0 Million BCM
-
Mining Phosphate quantities =1.3 Million BCM
-
Completion = 10 %
Scope of Work :
-
Overburden & internal waste Removal using excavator & wheal loader and transport the OB to the waste yards and cleaning with dozing.
-
Phosphate Mining , Cleaning by graders and dozers.
-
Transportation using dump truck to screen unit
-
Crushing & Screening Quantities
-
Operate (closed vibrating plant system) which high by max. the yield and min. rejection.
-
Feeding 50cm hopper by wheel loaders & dump trucks
-
Classification / separation of materials by Jaw & Rotary crusher
-
Crushing & sizing the materials to pass 100% of -4mm & -8mm
-
All materials handled by conveyor belts then transport product to piles
-
Mixing & blending the product to get the required homogenous
-
Drying the product by solar sun and wind energy to reduce moisture content.
-
Drying the product by Dryer unit to reduce moisture content (3%)
-
Hauling the oversize (reject) material to waste yards (Stockpiles) and dozing
-
Use wheel loader for loading dispatching trucks for direct shipping & transportation to Al Abiad Mine (17Km).
-
All productivity maintenance activities of conveyor belts and vibrating screens plants performed by in house team.